Lower Greenville Townhomes Progress

At the Lower Greenville-area townhomes, construction has continued to progress since our last update.  At 1831 Bennett, exterior work is almost complete, with only interior finish-out and site/landscaping work remaining.  At 5719 and 5907 Lindell, framing and exterior sheathing are complete and work is primarily focused around plumbing and electrical rough-ins along with the installation of windows and doors.  At 1821 Euclid, framing has mostly topped out and exterior sheathing is being installed.

1831 Bennett 2 5 COMPRESSED

5719 Lindell 2 5 COMPRESSED

5907 Lindell 2 5 COMPRESSED

1821 Euclid 2 5 COMPRESSED