Grayson-Collin Electric Cooperative Progress

Construction is rapidly approaching completion at Grayson-Collin Electric Cooperative's new headquarters in Van Alstyne.  Around the exterior of the campus, remaining work consists of the installation of flatwork and landscaping.  In the interior of the office building, remaining finishing touches are being completed, and furniture installation is taking place throughout the facility with a goal of Grayson-Collin Electric moving into their new home by month's end.

Grayson 1 10 18 1 D

Grayson 1 10 18 2 D

Grayson 1 10 18 3 D

Grayson 1 10 18 4 D

Continue reading
  315 Hits
  0 Comments
315 Hits
0 Comments

Richardson Bike Mart of McKinney Progress

Since our last update, construction has greatly progressed along at Richardson Bike Mart's new store in McKinney.  Over the past several weeks, most steel has been erected at the site and exterior framing has begun.  In addition, a CMU wall separating the bike shop from an adjacent LA Fitness has been completed, and structural work is taking place at the parapets around the perimeter of the building.  Over the coming weeks, we will see the installation of exterior sheathing and masonry taking place, which will allow the building to be "dryed in" and interior work to begin.

Richardson Bike Mart 1 5 18 1 COMPRESSED

Richardson Bike Mart 1 5 18 2 COMPRESSED

Richardson Bike Mart 1 5 18 3 COMPRESSED

Richardson Bike Mart 1 5 18 4 COMPRESSED

Continue reading
  381 Hits
  0 Comments
381 Hits
0 Comments

First Baptist Wylie Progress

At First Baptist Wylie, construction is continuing to move along across the site.  The adult education classrooms which were being renovated in the first phase of work are now complete and in use by the church.  In the existing gym, the second floor slab has been filled in and walls have been framed for classrooms and multipurpose spaces.  In addition, mechanical, electrical and plumbing rough ins are mostly complete.  Currently, acoustical insulation between the classrooms is being installed, preparing for the walls to be closed up.  Most visibly, construction is primarily centered at the new construction portion of the project.  Slabs for new circulation atriums have been poured, and structural steel is currently being erected.  Over the coming weeks, these spaces will begin to take their final shape, and will ultimately simplify circulation throughout the church campus.

FBW 12 28 17 1 REDONE COMPRESSED

FBW 12 28 17 2 REDONE COMPRESSED

Continue reading
  354 Hits
  0 Comments
354 Hits
0 Comments

Lower Greenville Townhomes Progress

Since our last update, construction has visibly progressed at all four Lower Greenville-area townhome projects.  At 1831 Bennett, exterior windows and doors have been installed, and the installation of exterior materials is beginning to give the project its final appearance.  In addition, interior work is beginning to take place as the building is sealed up.  At 5719 and 5907 Lindell, framing and exterior sheathing are almost complete, and we will be seeing the installation of windows, doors and exterior materials over the coming weeks.  In addition, mechanical, electrical and plumbing rough-ins will be taking place.  At 1821 Euclid, framing is continuing to take shape at the second floor, and will continue to move vertically.

1831 Bennett 12 12 COMPRESSED

5719 Lindell 12 12 COMPRESSED

5907 Lindell 12 12 COMPRESSED

1821 Euclid 12 12 COMPRESSED

Continue reading
  356 Hits
  0 Comments
356 Hits
0 Comments

Advantage Academy Progress

Construction is continuing to move along at Advantage Academy's campus expansion in Dallas.  At the new administrative wing connecting the two existing office/classroom buildings on the site, the slab is complete and framing has begun.  In addition, framing for a new cafeteria wing at the south end of the site is set to begin soon.  At the existing office building which is currently under renovation for classrooms, new Hardie panels are being installed around the parapets of the building to mirror the exterior materials of the expansions.  The other similar building which is currently in use will be renovated for new classrooms during this summer while school is out of session.  Over the coming weeks, framing work will continue to progress on the expansion spaces, while a new fire line and fire lane are also set to be installed through the site.

Advantage 12 5 17 1 COMPRESSED

Advantage 12 5 17 2 COMPRESSED

Advantage 12 5 17 3 COMPRESSED

Advantage 12 5 17 4 COMPRESSED

Advantage 12 5 17 5 COMPRESSED

Advantage 11 17 17 6 COMPRESSED

Continue reading
  354 Hits
  0 Comments
354 Hits
0 Comments

Lower Greenville Townhomes Progress

McCarthy Architecture wishes you a happy and restful Thanksgiving!  Today we have a construction update for the Lower Greenville area townhomes.

Over the past several weeks, construction has shown visible progress at all four townhome projects.  At 1831 Bennett Avenue, windows have been installed since our last visit, and mechanical and plumbing rough-ins are mostly complete.  At 5719 Lindell, framing and exterior sheathing are both almost complete, and work will be progressing to the interior in the coming weeks.  At 5907 Lindell, fourth floor framing is taking place, with construction moving towards the instalaltion of exterior sheathing once this is complete.  At 1821 Euclid, first floor framing and steel are complete, and the structure will be soon taking shape verticially.

1831 Bennett 11 22 COMPRESSED

5719 Lindell 11 22 COMPRESSED

5907 Lindell 11 22 COMPRESSED

1821 Euclid 11 22 COMPRESSED

Continue reading
  350 Hits
  0 Comments
350 Hits
0 Comments

Advantage Academy Progress

Over the past several weeks, construction has rapidly progressed at Advantage Academy's Dallas campus expansion.  Recently, slabs for both an administrative wing and a new cafeteria wing were poured.  In addition, work for a parking lot and drive area has begun, and these will be poured as site access permits.  At an existing office building which is being renovated for classrooms, framing is now complete, and rough-ins for mechanical, plumbing, electrical and data are taking place.  In the coming weeks, framing will also be taking place for the new expansion spaces.

Advantage 11 17 17 1 COMPRESSED

Advantage 11 17 17 2 COMPRESSED

Advantage 11 17 17 3 COMPRESSED

Advantage 11 17 17 4 COMPRESSED

Advantage 11 17 17 5 COMPRESSED

Advantage 11 17 17 6 COMPRESSED

Continue reading
  352 Hits
  0 Comments
352 Hits
0 Comments

Grayson-Collin Electric Cooperative Progress

Construction is continuing to progress along at Grayson-Collin Electric Cooperative's new headquarters in Van Alstyne.  At the exterior of the office building, soffit panels are being installed around the roof's perimeter, leaving sitework and landscaping remaining.  In the interior of the office building, grids for lay-in ceilings have been installed, and the installation of electrical fixtures, millwork and mechanical equipment is taking place.  In addition, the multipurpose room is beginning to take its final shape with the installation of suspended ceiling "clouds.  At both the warehouse and maintenance buildings, construction is almost complete, with only varying punch-list items remaining.

Grayson 11 9 17 1 COMPRESSED

Grayson 11 9 17 2 COMPRESSED

Grayson 11 9 17 3 COMPRESSED

Grayson 11 9 17 4 COMPRESSED

Grayson 11 9 17 5 COMPRESSED

Grayson 11 9 17 6 COMPRESSED

Grayson 11 9 17 7 COMPRESSED

Continue reading
  346 Hits
  0 Comments
346 Hits
0 Comments

Grayson-Collin Electric Cooperative Progress

Construction is continuing to progress along at Grayson-Collin Electric Cooperative's new headquarters in Van Alstyne.  At the exterior of the office building, brick and stone veneers are complete, and metal paneling has been installed across the facade.  In the interior of the office building, finish-out work is continuing with the installation of lay-in ceilings, tile and other interior finishes, mechanical and electrical equipment, among other trades.  Over the coming weeks, work will be primarily be concentrated on the interior of the office building, with work at the warehouse and maintenance buildings almost complete.

Grayson 10 27 17 1 COMPRESSED

Grayson 10 27 17 2 COMPRESSED

Grayson 10 27 17 3 COMPRESSED

Grayson 10 27 17 4 COMPRESSED

Grayson 10 27 17 5 COMPRESSED

Grayson 10 27 17 6 COMPRESSED

Grayson 10 27 17 7 COMPRESSED

Continue reading
  323 Hits
  0 Comments
323 Hits
0 Comments

Advantage Academy Progress

Construction is continuing to progress along at Advantage Academy's Dallas campus expansion.  At an existing office building, an existing mansard roof has been removed, alowing for the construction of a new parapet to reflect the aesthetic of new buildings to be constructed on the site.  In the interior of this space, new walls are being framed for classrooms and offices.  In addition, across the site, site preparations and earthwork have begun at the locations of future buildings and parking areas.

Advantage 10 20 17 1 COMPRESSED

Advantage 10 20 17 2 COMPRESSED

Advantage 10 20 17 3 COMPRESSED

Advantage 10 20 17 4 COMPRESSED

Advantage 10 20 17 5 COMPRESSED

Continue reading
  318 Hits
  0 Comments
318 Hits
0 Comments

Richardson Bike Mart of McKinney

McCarthy Architecture is excited to be a part of the realization of a new retail space for Richardson Bike Mart in McKinney.  So far, construction efforts have focused around site preparation.  Currently, piers are being staked in preparation for drilling and pouring which will take place over the next couple of weeks.   In addition, a portion of the site has been excavated to allow for the relocation of an existing sanitary sewer line serving an adjacent LA Fitness.

Richardson Bike Mart 10 18 17 1 COMPRESSED

Richardson Bike Mart 10 18 17 2 COMPRESSED

Richardson Bike Mart 10 18 17 3 COMPRESSED

Richardson Bike Mart 10 18 17 4 COMPRESSED

Richardson Bike Mart 10 18 17 5 COMPRESSED

Continue reading
  453 Hits
  0 Comments
453 Hits
0 Comments

Lower Greenville Townhomes Progress

Construction is continuing to progress along at the Lower Greenville area townhomes.  At 1831 Bennett Avenue, exterior framing and sheathing is complete, and interior mechanical/plumbing/electrical rough-ins will begin soon.  In addition, the installation of doors, windows and exterior finish materials will be visible from the street.  At 5719 Lindell, second floor framing is complete, and the structure is beginning to take shape vertically.  At 5907 Lindell, steel and framing at the first floor is complete, and second floor framing should begin soon.  At 1821 Euclid, steel to support the cantilevered upper floors is complete, and framing will continue to progress along.

1831 Bennett 10 13 COMPRESSED

5719 Lindell 10 13 COMPRESSED

5907 Lindell 10 13 COMPRESSED

1821 Euclid 10 13 COMPRESSED

Continue reading
  319 Hits
  0 Comments
319 Hits
0 Comments

Grayson-Collin Electric Cooperative Progress

Construction is continuing to progress along at Grayson-Collin Electric Cooperative's new headquarters in Van Alstyne.  At the exterior of the office building, brick and stone veneers are almost complete, and the exterior as a whole is beginning to take on its final aesthetic.  In the interior of the office building, finish-out work is continuing with the installation of door frames, ceilings, mechanical and electrical equipment, among other trades.  At both the warehouse and maintenance buildings, exterior work is essentially complete and interior-finish out work is quickly approaching completion, with only certain fixtures and finishes remaining.

Grayson 10 6 17 1 COMPRESSED

Grayson 10 6 17 2 COMPRESSED

Grayson 10 6 17 3 COMPRESSED

Grayson 10 6 17 4 COMPRESSED

Grayson 10 6 17 5 COMPRESSED

Grayson 10 6 17 6 COMPRESSED

Grayson 10 6 17 7 COMPRESSED

Grayson 10 6 17 8 COMPRESSED

Grayson 10 6 17 9 COMPRESSED

Continue reading
  238 Hits
  0 Comments
238 Hits
0 Comments

Advantage Academy Progress

At Advantage Academy's Dallas campus, construction is continuing to progress along on the charter school's campus expansion.  Interior demolition within an existing office building has been completed, and the existing mansard roof at this building is in the process of being removed.  In addition, the large retaining wall at the back of the site has been completed along with a new fence, and a new storm sewer line is being installed in the area.

Advantage 9 20 17 1 COMPRESSED

Advantage 9 20 17 2 COMPRESSED

Advantage 9 20 17 3 COMPRESSED

Advantage 9 20 17 4 COMPRESSED

Advantage 9 20 17 5 COMPRESSED

Continue reading
  286 Hits
  0 Comments
286 Hits
0 Comments

Lower Greenville Townhomes Progress

Construction is continuing to progress along at the Lower Greenville area townhomes.  At 1831 Bennett Avenue, framing has progressed to the fourth floor and should be complete in the coming weeks.  In addition, structural steel has been placed to support upper level patios.  At 5719 Lindell and 5907 Lindell, steel has been installed to support cantilivering of the upper floors over a drive lane, and the upper floors will begin framing soon.  At 1821 Euclid, first floor framing has begun to take shape.

1831 Bennett 9 13 COMPRESSED

5719 Lindell 9 13 COMPRESSED

5907 Lindell 9 13 COMPRESSED

1821 Euclid 9 13 COMPRESSED

Continue reading
  257 Hits
  0 Comments
257 Hits
0 Comments

First Baptist Wylie Progress

Construction recently broke ground for a large expansion and renovation project at First Baptist Wylie.  This project consists of several components, including the repurposing of an existing gym for a new childrens' wing, renovations to adult education spaces and the development of atriums which improve circulation throughout the church campus.  The first phase of the project consisted of demolishing a 1960's era classroom building which was in disrepair and greatly hampered traffic flow.  This was an intricate process, as this existing building had to be taken down without disturbing any adjacent structures.  In addition to the demolition of this building, construction is also progressing in both the future childrens' and adult education spaces.

FBW 9 8 17 1 COMPRESSED

FBW 9 8 17 2 COMPRESSED

FBW 9 8 17 3 COMPRESSED

FBW 9 8 17 4 COMPRESSED

FBW 9 8 17 5 COMPRESSED

FBW 9 8 17 6 COMPRESSED

Continue reading
  269 Hits
  0 Comments
269 Hits
0 Comments

Grayson-Collin Electric Cooperative Progress

Construction is rapidly moving forward at Grayson-Collin Electric Cooperative's new headquarters in Van Alstyne.  At the exterior of the office building, brick and stone veneers are progressing along with the standing seam metal roof, bringing the project much closer to its final appearance.  On the interior of the office building, partition walls and gypsum board are being installed, and the interior spaces are beginning to take shape.  At both the warehouse and maintenance buildings, interior finish-out is taking place and both buildings are approaching completion.

Grayson 9 6 17 1 COMPRESSED

Grayson 9 6 17 2 COMPRESSED

Grayson 9 6 17 3 COMPRESSED

Grayson 9 6 17 4 COMPRESSED

Grayson 9 6 17 5 COMPRESSED

Grayson 9 6 17 6 COMPRESSED

Continue reading
  257 Hits
  0 Comments
257 Hits
0 Comments

Advantage Academy

Recently, construction at Advantage Academy's Dallas campus broke ground for a large renovation and expansion project.  So far, interior work has consisted of demolition within an existing office building adjacent to the current school campus.  In addition, construction on a retaining wall at the back of the site has commenced.

Advantage 8 25 17 1

Advantage 8 25 17 2

Advantage 8 25 17 3

Advantage 8 25 17 4

Advantage 8 25 17 5

Continue reading
  347 Hits
  0 Comments
347 Hits
0 Comments

Grayson-Collin Electric Cooperative Progress

Over the last several weeks, construction has rapidly moved along at Grayson-Collin Electric Cooperative's new headquarters in Van Alstyne.  At the office building, all exterior walls have been framed and both sheathing and stone/brick veneer are being installed.  In addition, the hardened area has been completed, and other interior walls are being framed throughout the facility.  At the warehouse building, exterior work is almost complete and interior finish-out is taking place.  Similarly, the maintenance building is rapidly approaching completion, with primarily interior work remaining.

Grayson 8 11 1 COMPRESSED

Grayson 8 11 2 COMPRESSED

Grayson 8 11 3 COMPRESSED

Grayson 8 11 4 COMPRESSED

Grayson 8 11 5 COMPRESSED

Grayson 8 11 6 COMPRESSED

Grayson 8 11 7 COMPRESSED

Continue reading
  308 Hits
  0 Comments
308 Hits
0 Comments

Lower Greenville Townhomes Progress

Construction has progressed along at the Lower Greenville area townhomes since our last visit.  At 1831 Bennett Avenue, structural steel to support patios on the third floor of each townhouse has been placed, and preparations are underway for the third floor framing.  At 5719 Lindell and 5907 Lindell, first floor framing is nearing completion, and we should be seeing more vertical activity in the coming weeks.  At 1821 Euclid, the foundation has been poured since the last visit and framing is set to begin soon.

1831 Bennett 8 4

5719 Lindell 8 4

5907 Lindell 8 4

1821 Euclid 8 4

Continue reading
  270 Hits
  0 Comments
270 Hits